  • Goseong High thermal power plant construction ( castles Green Power Project)

    Work Scope
    PC
    Order
    SPC
    Period
    2015.09~2021.04
    Scale
    2,080MW (1,040 MW x 2)
    Perform Form
    IPP Sponsor+ EPC
    더보기

    5,6 Singori take underwater drainage structures construction construction

    Order
    Korea Hydro & Nuclear Power
    Period
    2015.03~2019.07
    Scale
    Intake Tunnel: 2 places 756m, 759m / Drainage Tunnel: 2 places 389m, 357m - Intake : 10 points , drain : 10 points - Intake Division: 1 point (L222m × B60m × H19.6m) Drainage Division: 2 points (L12m × B12m × H20.3m) - Nine working stations : 1 point
    더보기

    Tongyeong production base vaporization of liquefied natural gas transmission facilities construction work

    Period
    2011.12~2013.12
  • Gimcheon Community Energy Project

    Order
    Gimcheon Energy Co., Ltd
    Period
    2011.03~2013.07
    Scale
    * Power Bolier : 330t/h - Manufacturer : Hyundai HIC - Type : Circulating Fluidized-Bed * STG : 59MW x 1 (Siemens)
    더보기

    Shin(new) Hanul Nuclear Power Plant

    Shin(new) Hanul Nuclear Power Plant

    Order
    Korea Hydro & Nuclear Power
    Period
    2010.04~2019.02
    Commercialization
    Unit1 : 2018.04.30 , Unit2 : 2019.02.28
    Scale
    Advance Power Reactor 1,400MW x 2 Block
    Perform Form
    C
    더보기

    Shingori Nuclear Power Plant 1,2

    Order
    Korea Hydro&Nuclear Power Co.
    Period
    2005.02~2011.12
    Commercialization
    No. 1 : 2009. 5 / No. 2 : 2010. 3
    Scale
    - Generating Capacity 1,000MW grade 1, 2 - Type:PWR
    더보기
  • Shingori Nuclear Power Plant No. 1 & 2

    Period
    2005.02~2011.12
    Scale
    - Generating Capacity 1,000MW-grade No. 1&2
    더보기

    Gimhae Agro-Fisheries General Market Logistics Consulting

    Period
    2001.10~2002.01
    Scale
    2001.10-2002.01 Logistics Analysis
    더보기

    Gyungbuk Recycling Goods Storage Facility Construction(Phase 1)

    Period
    1998.12~1999.03
    Scale
    Korea Environment&Resources Corporation 98.12-99.3 Procurement, construction -Capa : 11,600Cells(High Rack)
    더보기
  • Automated Storage Warehouse for Blending (Ulsan)

    Period
    1998.11~1999.06
    Scale
    Fuchs-Oil Korea 98.11-99.06 Turn-Key -Capa : 1,200Cells -Stacker Crane : 2 units
    더보기

    1st AS/RS REVAMP

    Period
    1997.08~1998.09
    Scale
    - Location :Ulsan - Started :1997. 8 - Completed :1998. 9 - Work Amount - Storage amount : 3000cell - Bagging Machine : 4 ea - Palletizer : 4 ea - A.G.V : 25 ea

    VOC Reduction Facility

    Period
    1997.06~1999.12
    Scale
    - Location | Ulsan - Started | 1997. 6 - Completed | 1999. 12 - Work Amount | VOC(Volatile Organic Compound) Reduction Facility

Goseong High thermal power plant construction ( castles Green Power Project)

The Business Performance details view. can you check Work Scope, Order, Period
· Location Goseong-gun, Gyeongsangnam-do, Korea
· Work Scope PC
· Order SPC
· Period 2015.09~2021.04
· Scale 2,080MW (1,040 MW x 2)
· Perform Form IPP Sponsor+ EPC

5,6 Singori take underwater drainage structures construction construction

The Business Performance details view. can you check Work Scope, Order, Period
· Location Sinam-ri, Seosaeng-myeon, Ulju-gun, Ulsan, Korea
· Order Korea Hydro & Nuclear Power
· Period 2015.03~2019.07
· Scale Intake Tunnel: 2 places 756m, 759m / Drainage Tunnel: 2 places 389m, 357m - Intake : 10 points , drain : 10 points - Intake Division: 1 point (L222m × B60m × H19.6m) Drainage Division: 2 points (L12m × B12m × H20.3m) - Nine working stations : 1 point

Tongyeong production base vaporization of liquefied natural gas transmission facilities construction work

The Business Performance details view. can you check Work Scope, Order, Period
· Location Tongyeong-si, Gyeongsangnam-do, Korea
· Period 2011.12~2013.12

Gimcheon Community Energy Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gimcheon, Korea
· Order Gimcheon Energy Co., Ltd
· Period 2011.03~2013.07
· Scale * Power Bolier : 330t/h - Manufacturer : Hyundai HIC - Type : Circulating Fluidized-Bed * STG : 59MW x 1 (Siemens)

Shin(new) Hanul Nuclear Power Plant

  • Shin(new) Hanul Nuclear Power Plant
The Business Performance details view. can you check Work Scope, Order, Period
· Location Uljin, Korea
· Order Korea Hydro & Nuclear Power
· Period 2010.04~2019.02
· Commercialization Unit1 : 2018.04.30 , Unit2 : 2019.02.28
· Scale Advance Power Reactor 1,400MW x 2 Block
· Perform Form C

Shingori Nuclear Power Plant 1,2

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gijang-gun, Busan
· Order Korea Hydro&Nuclear Power Co.
· Period 2005.02~2011.12
· Commercialization No. 1 : 2009. 5 / No. 2 : 2010. 3
· Scale - Generating Capacity 1,000MW grade 1, 2 - Type:PWR

Shingori Nuclear Power Plant No. 1 & 2

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gijang-gun, Busan
· Period 2005.02~2011.12
· Scale - Generating Capacity 1,000MW-grade No. 1&2

Gimhae Agro-Fisheries General Market Logistics Consulting

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gimhae
· Period 2001.10~2002.01
· Scale 2001.10-2002.01 Logistics Analysis

Gyungbuk Recycling Goods Storage Facility Construction(Phase 1)

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gyeongbuk
· Period 1998.12~1999.03
· Scale Korea Environment&Resources Corporation 98.12-99.3 Procurement, construction -Capa : 11,600Cells(High Rack)

Automated Storage Warehouse for Blending (Ulsan)

The Business Performance details view. can you check Work Scope, Order, Period
· Location Ulsan
· Period 1998.11~1999.06
· Scale Fuchs-Oil Korea 98.11-99.06 Turn-Key -Capa : 1,200Cells -Stacker Crane : 2 units

1st AS/RS REVAMP

The Business Performance details view. can you check Work Scope, Order, Period
· Location Ulsan
· Period 1997.08~1998.09
· Scale - Location :Ulsan - Started :1997. 8 - Completed :1998. 9 - Work Amount - Storage amount : 3000cell - Bagging Machine : 4 ea - Palletizer : 4 ea - A.G.V : 25 ea

VOC Reduction Facility

The Business Performance details view. can you check Work Scope, Order, Period
· Location Ulsan
· Period 1997.06~1999.12
· Scale - Location | Ulsan - Started | 1997. 6 - Completed | 1999. 12 - Work Amount | VOC(Volatile Organic Compound) Reduction Facility