BUSINESS Business Performance

  • Ethylene Manufacturing Facility Project

    Order
    SK Corp.
    Period
    1987.10~1990.06
    Scale
    Ethylene 400,000 ton/year, Propylene 200,000 ton/year Hot Section Naphtha Cracking, Cold Section Fraction

    Butadiene Project

    Work Scope
    72,000 MTPY
    Order
    SK Corp. (Korea)
    Period
    1987.09~1989.09
    Scale
    72,000 MTPY
    Perform Form
    ED,PR CN,PS

    Phosphoric Acid Plant Expansion Project

    Order
    Namhea Chemical Co.
    Period
    1987.06~1988.06
    Scale
    1,100 Ton/Day
  • DMT/PTA Plant

    Work Scope
    160,000 MTPY
    Order
    Sk Chemical Co.
    Period
    1987.05~1989.08
    Scale
    - CTA : 247,200 Ton/Year - PTA : 160,000 Ton/Year - DMT : 10,000 Ton/Year
    Perform Form
    ED,PS,CN PR,CS,CO

    DMT/PTA Project

    Work Scope
    160,000 MTPY, 420,000 MTPY, 300,000 MTPY
    Order
    SK Chemical, (Korea)
    Period
    1987.05~1989.09
    Scale
    160,000 MTPY, 420,000 MTPY, 300,000 MTPY
    Perform Form
    ED,PS,CN PR,CS,CO

    Seoul Munjung Oylmpic Family Town Project

    Period
    1987.05~1988.12
    Scale
    56 Apartment Buildings of 13~15 Floors, 990 units of 4,494 units and other facilities 540 units of 32pyung,270 units of 49pyung, 180 units of 56pyung
    더보기
  • Busan Guseo Phase 2 SK Apartment Project

    Period
    1987.04~1988.05
    Scale
    3 Apartment Buildings of 15 Floors, 330units 210 units of 31pyung, 60 units of 32pyung, 60 units of 45pyung
    더보기

    Oil Transfer Pipeline for 55,000 bbl Storage Tanks and Utility

    Work Scope
    Capacity : - 12" Dia x 6 km, - 10" Dia x 4.5 km
    Order
    Yukong, Ltd, (Korea)
    Period
    1987.04~1988.06
    Scale
    Capacity : - 12" Dia x 6 km, - 10" Dia x 4.5 km
    Perform Form
    LSTK

    New Ethylene Plant Project

    Work Scope
    400,000 MTPY, 200,000 MTPY, 300,000 MTPY
    Order
    SK Corp. (Korea)
    Period
    1987.04~1989.11
    Scale
    400,000 MTPY, 200,000 MTPY, 300,000 MTPY
    Perform Form
    ED,PS CN,OA
  • SKC CD Plant Construction Project

    Period
    1985.11~1986.11
    Scale
    - Location | Cheonan-si, Chungnam - Started | 1985. 11 - Completed | 1986. 11 - Work Amount | Total Floor Area 22,848m2 Class 100 Vertical Lamina Fow Clean ROOM 528m2 Class 1,000- 10,000 7,512m2
    더보기

    Naphtha Cracking Facility Modernazation and Renovation

    Order
    SK Corp.
    Period
    1985.05~1987.06
    Scale
    155,000Ton/year Equipment Removal 250 Ton New Installation 425 Ton Relocation 450 Ton S/Structure 425 Ton
    더보기

    BTX Storage Tank

    Order
    SK Corp. Korea
    Period
    1984.09~1985.09
    Perform Form
    EPC LSTK

Ethylene Manufacturing Facility Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Ulsan
· Order SK Corp.
· Period 1987.10~1990.06
· Scale Ethylene 400,000 ton/year, Propylene 200,000 ton/year Hot Section Naphtha Cracking, Cold Section Fraction

Butadiene Project

The Business Performance details view. can you check Work Scope, Order, Period
· Work Scope 72,000 MTPY
· Order SK Corp. (Korea)
· Period 1987.09~1989.09
· Scale 72,000 MTPY
· Perform Form ED,PR CN,PS

Phosphoric Acid Plant Expansion Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Namhea, Gyungnam
· Order Namhea Chemical Co.
· Period 1987.06~1988.06
· Scale 1,100 Ton/Day

DMT/PTA Plant

The Business Performance details view. can you check Work Scope, Order, Period
· Location Ulsan
· Work Scope 160,000 MTPY
· Order Sk Chemical Co.
· Period 1987.05~1989.08
· Scale - CTA : 247,200 Ton/Year - PTA : 160,000 Ton/Year - DMT : 10,000 Ton/Year
· Perform Form ED,PS,CN PR,CS,CO

DMT/PTA Project

The Business Performance details view. can you check Work Scope, Order, Period
· Work Scope 160,000 MTPY, 420,000 MTPY, 300,000 MTPY
· Order SK Chemical, (Korea)
· Period 1987.05~1989.09
· Scale 160,000 MTPY, 420,000 MTPY, 300,000 MTPY
· Perform Form ED,PS,CN PR,CS,CO

Seoul Munjung Oylmpic Family Town Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location 180 area, Garak-dong, Songpa-gu, Seoul
· Period 1987.05~1988.12
· Scale 56 Apartment Buildings of 13~15 Floors, 990 units of 4,494 units and other facilities 540 units of 32pyung,270 units of 49pyung, 180 units of 56pyung

Busan Guseo Phase 2 SK Apartment Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location 185-1, Guseo-dong, Guemjung-gu, Busan
· Period 1987.04~1988.05
· Scale 3 Apartment Buildings of 15 Floors, 330units 210 units of 31pyung, 60 units of 32pyung, 60 units of 45pyung

Oil Transfer Pipeline for 55,000 bbl Storage Tanks and Utility

The Business Performance details view. can you check Work Scope, Order, Period
· Work Scope Capacity : - 12" Dia x 6 km, - 10" Dia x 4.5 km
· Order Yukong, Ltd, (Korea)
· Period 1987.04~1988.06
· Scale Capacity : - 12" Dia x 6 km, - 10" Dia x 4.5 km
· Perform Form LSTK

New Ethylene Plant Project

The Business Performance details view. can you check Work Scope, Order, Period
· Work Scope 400,000 MTPY, 200,000 MTPY, 300,000 MTPY
· Order SK Corp. (Korea)
· Period 1987.04~1989.11
· Scale 400,000 MTPY, 200,000 MTPY, 300,000 MTPY
· Perform Form ED,PS CN,OA

SKC CD Plant Construction Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Cheonan-si, Chungnam
· Period 1985.11~1986.11
· Scale - Location | Cheonan-si, Chungnam - Started | 1985. 11 - Completed | 1986. 11 - Work Amount | Total Floor Area 22,848m2 Class 100 Vertical Lamina Fow Clean ROOM 528m2 Class 1,000- 10,000 7,512m2

Naphtha Cracking Facility Modernazation and Renovation

The Business Performance details view. can you check Work Scope, Order, Period
· Location Ulsan
· Order SK Corp.
· Period 1985.05~1987.06
· Scale 155,000Ton/year Equipment Removal 250 Ton New Installation 425 Ton Relocation 450 Ton S/Structure 425 Ton

BTX Storage Tank

The Business Performance details view. can you check Work Scope, Order, Period
· Order SK Corp. Korea
· Period 1984.09~1985.09
· Perform Form EPC LSTK