  • Army Gapyeong Yangju BTL

    Period
    2014.04~2016.06
    Scale
    Articles in 2 places , 2 places of accommodation officers, military dormitory 4 places
    더보기

    SKMS 2nd Research Institute

    Period
    2014.03~2015.11
    Scale
    Land Area : 31,266 pyung , Gross Area : 5,219 pyung Group Research Building , private research building , the same facilities , etc

    SK Hynix Icheon women's dormitory

    Period
    2014.03~2015.08
    Scale
    Land Area : 7,535 pyung Gross Area : 30,219 pyung
    더보기
  • M14 Project PH-1 Project

    Order
    SK Hynix
    Period
    2014.03~2015.07
    Scale
    - Based on the world's largest single- Fab - 66,000M2, 2 -layer structure clean room
    Perform Form
    EPC
    더보기

    Highway above the 14 line between Ulsan , Miryang - construction (fifth section)

    Order
    Korea Highway Corporation
    Period
    2014.02~2021.02
    Scale
    Total length L = 8.02km 1) Tunnel : 7,947km / 1 places 2) Earthwork : Cut 168,652m3 3) drain hole : the drain pipe (55.9m / 5 places) , culverts (15.6m / 1 places) 4) Ball Packaging : Packaging of cement (50,330m3), asphalt concrete pavement (3a) 5) ball bag : 1 set
    더보기

    Median line Dodam- Youngcheon second double track train roadbed construction tools

    Order
    Korea Rail Network Authority
    Period
    2014.01~2017.06
    Scale
    [ Total length : L = 14.675㎞] - Tunnel : L = 11.165㎞ (2 points inclined Gang) - Earthwork : L = 2.850㎞ - Bridge : L = 0.660㎞ (5 places) - Orbit : Main Line
    더보기
  • Guseo SK VIEW

    Period
    2014.01~2016.02
    Scale
    3 floors below ground, 17-24 floors above ground 693 units in 8 buildings Gross Area: 120,669.81㎡
    더보기

    Dream Forest SK VIEW

    Period
    2014.01~2016.03
    Scale
    2 floors below ground, 20 floors above ground 504 units in 6 buildings Gross Area: 79,960.93㎡
    더보기

    Siheung Mokgam B-6BL Apt.

    Period
    2014.01~2016.05
    더보기
  • Godeok green energy fuel cell power plant construction ( Godeok fuel cell power plants)

    Order
    Godeok green energy Co., Ltd.
    Period
    2013.12~2014.12

    Pyeongtaek facility construction brigade barracks

    Period
    2013.12~2015.12
    Scale
    Land Area : 18,852 pyung, 10,554 pyung, barracks facilities, accommodation, restaurants copper
    더보기

    Hanam heat supply facilities construction work

    Order
    Hanam Energy Services Co., Ltd.
    Period
    2013.11~2015.10
    Commercialization
    2015.10.31 
    Scale
    398.9MW
    Perform Form
    EPC 
    더보기

Army Gapyeong Yangju BTL

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gapyeong-gun / Yangju-si / Uijeongbu-si, Gyeonggi-do, Korea
· Period 2014.04~2016.06
· Scale Articles in 2 places , 2 places of accommodation officers, military dormitory 4 places

SKMS 2nd Research Institute

The Business Performance details view. can you check Work Scope, Order, Period
· Location 382-7, Jangcheon-ri, Seolseong-myeon, Icheon-si, Gyeonggi-do, Korea
· Period 2014.03~2015.11
· Scale Land Area : 31,266 pyung , Gross Area : 5,219 pyung Group Research Building , private research building , the same facilities , etc

SK Hynix Icheon women's dormitory

The Business Performance details view. can you check Work Scope, Order, Period
· Location 1-9, Daeheung-ri, Daewol-myeon, Icheon-si, Gyeonggi-do, Korea
· Period 2014.03~2015.08
· Scale Land Area : 7,535 pyung Gross Area : 30,219 pyung

M14 Project PH-1 Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Icheon-si, Gyeonggi-do, Korea
· Order SK Hynix
· Period 2014.03~2015.07
· Scale - Based on the world's largest single- Fab - 66,000M2, 2 -layer structure clean room
· Perform Form EPC

Highway above the 14 line between Ulsan , Miryang - construction (fifth section)

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gorye-ri, Danjang-myeon, Miryang-si ~ Seon-ri, Wondong-myeon, Yangsan-si, Gyeongsangnam-do, Korea
· Order Korea Highway Corporation
· Period 2014.02~2021.02
· Scale Total length L = 8.02km 1) Tunnel : 7,947km / 1 places 2) Earthwork : Cut 168,652m3 3) drain hole : the drain pipe (55.9m / 5 places) , culverts (15.6m / 1 places) 4) Ball Packaging : Packaging of cement (50,330m3), asphalt concrete pavement (3a) 5) ball bag : 1 set

Median line Dodam- Youngcheon second double track train roadbed construction tools

The Business Performance details view. can you check Work Scope, Order, Period
· Location Daegang-myeon, Danyang-gun, Chungbuk ~ Punggi-eup, Yeongju-si, Gyeongbuk, Korea.
· Order Korea Rail Network Authority
· Period 2014.01~2017.06
· Scale [ Total length : L = 14.675㎞] - Tunnel : L = 11.165㎞ (2 points inclined Gang) - Earthwork : L = 2.850㎞ - Bridge : L = 0.660㎞ (5 places) - Orbit : Main Line

Guseo SK VIEW

The Business Performance details view. can you check Work Scope, Order, Period
· Location 26, Geumgang-ro 391beon-gil, Geumjeong-gu, Busan, Korea
· Period 2014.01~2016.02
· Scale 3 floors below ground, 17-24 floors above ground 693 units in 8 buildings Gross Area: 120,669.81㎡

Dream Forest SK VIEW

The Business Performance details view. can you check Work Scope, Order, Period
· Location 20, Wolgye-ro 44da-gil, Nowon-gu, Seoul, Korea
· Period 2014.01~2016.03
· Scale 2 floors below ground, 20 floors above ground 504 units in 6 buildings Gross Area: 79,960.93㎡

Siheung Mokgam B-6BL Apt.

The Business Performance details view. can you check Work Scope, Order, Period
· Period 2014.01~2016.05

Godeok green energy fuel cell power plant construction ( Godeok fuel cell power plants)

The Business Performance details view. can you check Work Scope, Order, Period
· Location Gangdong-gu, Seoul, Korea
· Order Godeok green energy Co., Ltd.
· Period 2013.12~2014.12

Pyeongtaek facility construction brigade barracks

The Business Performance details view. can you check Work Scope, Order, Period
· Location 12 Mt, Dongchang-ri, Paengseong-eup, Pyeongtaek-si, Gyeonggi-do, Korea U.S. military base relocation project premises, Paengseong-eup, Pyeongtaek-si, Gyeonggi-do, Korea
· Period 2013.12~2015.12
· Scale Land Area : 18,852 pyung, 10,554 pyung, barracks facilities, accommodation, restaurants copper

Hanam heat supply facilities construction work

The Business Performance details view. can you check Work Scope, Order, Period
· Location Hanam-si, Gyeonggi-do, Korea
· Order Hanam Energy Services Co., Ltd.
· Period 2013.11~2015.10
· Commercialization 2015.10.31 
· Scale 398.9MW
· Perform Form EPC