  • Yongma Privately Financed Construction Projects a tunnel.

    Order
    Yongma tunnel Corp.,
    Period
    2009.11~2014.11
    Scale
    - Extension L = 3.56km - 1 point tunnel (2.5km) - Three places Bridges
    더보기

    Construction of the roadbed for section 2-2 of the Honam High-Speed Railway

    Order
    Korea Rail Network Authority
    Period
    2009.11~2013.06
    Scale
    - Length 10.3km - 6 bridges (5.34㎞) - Earthwork: 8 locations (4.90㎞) - One tunnel (0.06㎞)
    더보기

    Section 20 (T/K) of the Nakdong River Revival Project

    Order
    Korea Water Resources Corporation
    Period
    2009.10~2011.12
    Scale
    - Total length: 21.21Km - Movable weir: 138m (including piers) - Fixed weir: 184.5m - Fishway: One natural/Borland fishway - Kong-do Public bridge: 675m - Improvement of the river channel: dredge amount (18,940,000㎥) - 2 Bridge protection structures (Yulji bridge, Jeokpo bridge) - 4 riverbed maintenance structures (Hwang River, etc.) - Ecological stream: one - 11 water pumps and distribution system - Structures: 3 buildings including the integrated management bldg., etc. - Pump/storage power station: 2,500Kw×2
    더보기
  • Section 7 (T/K) of the Geum River Revival Project

    Order
    Daejeon Regional Construction and Management Administration, Korea Water Resources Corporation
    Period
    2009.10~2011.12
    Scale
    - Length: 26.3km - Natural river improvement Improvement of the river channel (10.2 million ㎥) 18 interbed-storage protection structures 4 pier protection structures 52 drainage and sluice gates 4 water pumps and distribution system - Ecological stream - Multi-purpose movable weir (L=260M, H=7M) - pump/storage power station (1500KW×2기) - Structure (superintendent’s office)
    더보기

    Construction of the Ulsan-Pohang section (section 9) of National Highway No. 65

    Order
    Korea Expressway Corporation
    Period
    2009.06~2014.06
    Scale
    - Total length: 5.54Km - Earthwork * Cutting: 1,831㎥ * Banking: 1,660㎥ - Bridges: 918m (3 locations) - Tunnel: 733m (2 locations) - Supplementary facilities: service area (one location)
    더보기

    Construction (T/K) of facilities in Section 6 of the Gyeongin Ara Waterway Project

    Order
    Korea Water Resources Corporation
    Period
    2009.06~2011.12
    Scale
    - 4 container berths: 1.2km - Sore protection: 4,923m - Road facilities: 5.8km/10 location - Han River floodgate: 5 mitergates - Unloading facilities: (2 WSG cranes) - Structures: Passenger terminal bldg. and 8 other buildings
    더보기
  • SingaporeDowntownLineStage-2Contract915

    Order
    Land Transport Authority (LTA)
    Period
    2009.06~2015.11
    Scale
    - TBM Tunnel : 2.3km (2Line) - Cut & Cover Structure(30m×164m) - Cross Passage(NATM) : 9 Nos

    Gimje in vitro alternative Route detours(Heungsa-Yeonjeong) construction

    Order
    Iksan Regional Construction Management Administration
    Period
    2009.06~2016.05
    Scale
    - Extended 10.32km (B = 20m) - Bridge 21 places (801m) - Cloverleaf 4 places - Culvert 58 points (1,815m) - Soft ground 4.07㎞
    더보기

    Singapore, Down Town Line 2 C915 Project

    Order
    Land Transport Authority
    Period
    2009.06~2015.12
    Scale
    1. TBM Tunnel: 2.3 km 2 Lane (TBM 3 units) 2. Hume Shell Station: 30m × 164m 3. Cross Passage: Tunnel section 2 points 7 points (NATM) / C & C segment
    더보기
  • Singapore Downtown Line Stage-2 Contract 915

    Order
    Land Transport Authority (LTA)
    Period
    2009.06~2015.11
    Scale
    - TBM Tunnel: 2.3km (Line 2) - Cut & Cover Structure (30m×164m) - Cross Passage (NATM): 9 Nos
    더보기

    Incheon Metropolitan Urban Railroad Line2

    Incheon Metropolitan Urban Railroad Line2

    Order
    Incheon Metropolitan City
    Period
    2009.06~2016.10
    Scale
    - Total Length 1.890km - Tunnel 1.630km - Station 2ea - Ventilation 6ea
    Perform Form
    Bidding
    더보기

    Construction of Section 1-1 of the Honam High-Speed Railroad

    Order
    Korea Rail Network Authority
    Period
    2009.05~2013.05
    Scale
    - Total length: 7.9Km - Earthwork: 3.2Km - Bridges: 3.5Km (6 locations) - Tunnel: 1.16Km (NATM)
    더보기

Yongma Privately Financed Construction Projects a tunnel.

The Business Performance details view. can you check Work Scope, Order, Period
· Location Jungnang-gu, Seoul, Korea
· Order Yongma tunnel Corp.,
· Period 2009.11~2014.11
· Scale - Extension L = 3.56km - 1 point tunnel (2.5km) - Three places Bridges

Construction of the roadbed for section 2-2 of the Honam High-Speed Railway

The Business Performance details view. can you check Work Scope, Order, Period
· Location 358, Sindang-ri, Gwangseok-myeon, Nonsan, Southern Chungcheong-do
· Order Korea Rail Network Authority
· Period 2009.11~2013.06
· Scale - Length 10.3km - 6 bridges (5.34㎞) - Earthwork: 8 locations (4.90㎞) - One tunnel (0.06㎞)

Section 20 (T/K) of the Nakdong River Revival Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location 420, Hyeonchang-ri, Changnyeong-gun, Souther Gyeongsang-do
· Order Korea Water Resources Corporation
· Period 2009.10~2011.12
· Scale - Total length: 21.21Km - Movable weir: 138m (including piers) - Fixed weir: 184.5m - Fishway: One natural/Borland fishway - Kong-do Public bridge: 675m - Improvement of the river channel: dredge amount (18,940,000㎥) - 2 Bridge protection structures (Yulji bridge, Jeokpo bridge) - 4 riverbed maintenance structures (Hwang River, etc.) - Ecological stream: one - 11 water pumps and distribution system - Structures: 3 buildings including the integrated management bldg., etc. - Pump/storage power station: 2,500Kw×2

Section 7 (T/K) of the Geum River Revival Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location 890, Cheongryong-ri, Euidang-myeon, Gongju, Southern Chungcheong-do
· Order Daejeon Regional Construction and Management Administration, Korea Water Resources Corporation
· Period 2009.10~2011.12
· Scale - Length: 26.3km - Natural river improvement Improvement of the river channel (10.2 million ㎥) 18 interbed-storage protection structures 4 pier protection structures 52 drainage and sluice gates 4 water pumps and distribution system - Ecological stream - Multi-purpose movable weir (L=260M, H=7M) - pump/storage power station (1500KW×2기) - Structure (superintendent’s office)

Construction of the Ulsan-Pohang section (section 9) of National Highway No. 65

The Business Performance details view. can you check Work Scope, Order, Period
· Location 633-2, Andong-ri, Yangbuk-myeon, Gyeongju, Northern Gyeongsang-do
· Order Korea Expressway Corporation
· Period 2009.06~2014.06
· Scale - Total length: 5.54Km - Earthwork * Cutting: 1,831㎥ * Banking: 1,660㎥ - Bridges: 918m (3 locations) - Tunnel: 733m (2 locations) - Supplementary facilities: service area (one location)

Construction (T/K) of facilities in Section 6 of the Gyeongin Ara Waterway Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location 454-24, Singok-ri, Gochon-eup, Gimpo, Gyeonggi-do
· Order Korea Water Resources Corporation
· Period 2009.06~2011.12
· Scale - 4 container berths: 1.2km - Sore protection: 4,923m - Road facilities: 5.8km/10 location - Han River floodgate: 5 mitergates - Unloading facilities: (2 WSG cranes) - Structures: Passenger terminal bldg. and 8 other buildings

SingaporeDowntownLineStage-2Contract915

The Business Performance details view. can you check Work Scope, Order, Period
· Location 200 Petir Road Singapore 678271 SK E&C Project Office
· Order Land Transport Authority (LTA)
· Period 2009.06~2015.11
· Scale - TBM Tunnel : 2.3km (2Line) - Cut & Cover Structure(30m×164m) - Cross Passage(NATM) : 9 Nos

Gimje in vitro alternative Route detours(Heungsa-Yeonjeong) construction

The Business Performance details view. can you check Work Scope, Order, Period
· Location Baeksan-myeon, Gimje-si, Jeollabuk-do, Korea
· Order Iksan Regional Construction Management Administration
· Period 2009.06~2016.05
· Scale - Extended 10.32km (B = 20m) - Bridge 21 places (801m) - Cloverleaf 4 places - Culvert 58 points (1,815m) - Soft ground 4.07㎞

Singapore, Down Town Line 2 C915 Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location 320A Upper Bukit Timah Road Singapore 588217
· Order Land Transport Authority
· Period 2009.06~2015.12
· Scale 1. TBM Tunnel: 2.3 km 2 Lane (TBM 3 units) 2. Hume Shell Station: 30m × 164m 3. Cross Passage: Tunnel section 2 points 7 points (NATM) / C & C segment

Singapore Downtown Line Stage-2 Contract 915

The Business Performance details view. can you check Work Scope, Order, Period
· Location 200 Petir Road, Singapore, 678271, SK E&C Project Office
· Order Land Transport Authority (LTA)
· Period 2009.06~2015.11
· Scale - TBM Tunnel: 2.3km (Line 2) - Cut & Cover Structure (30m×164m) - Cross Passage (NATM): 9 Nos

Incheon Metropolitan Urban Railroad Line2

  • Incheon Metropolitan Urban Railroad Line2
The Business Performance details view. can you check Work Scope, Order, Period
· Location Incheon Metropolitan City, Korea
· Order Incheon Metropolitan City
· Period 2009.06~2016.10
· Scale - Total Length 1.890km - Tunnel 1.630km - Station 2ea - Ventilation 6ea
· Perform Form Bidding

Construction of Section 1-1 of the Honam High-Speed Railroad

The Business Performance details view. can you check Work Scope, Order, Period
· Location 269-6, Darak-ri, Gangnae-myeon, Cheongwon-gun, Northern Chungcheong-do
· Order Korea Rail Network Authority
· Period 2009.05~2013.05
· Scale - Total length: 7.9Km - Earthwork: 3.2Km - Bridges: 3.5Km (6 locations) - Tunnel: 1.16Km (NATM)