  • Gumi Industrial Parks Arterial Road Construction Phase 1

    Order
    Korea Water Resource Corp.
    Period
    1989.12~1993.07
    Scale
    Road Expansion L= 13.68Km B=18.5m Earth Work: Cutting 95,062m3 Banking 308,435m3 Drainage Work : Drainage pipe 2,346m 60ea, Conduit 69m 43ea Structure Work: Bridge 447.17m 4ea Pavement Work: Surface 2,505a Base 2,318a
    더보기

    Changwon-Jangyoo Road Construction Project

    Order
    Gyungnam
    Period
    1989.11~1994.02
    Scale
    Road expansion L=6.96Km B=12.0m Earth Work: Cutting 646,082m3 Banking 403,879m3 Drainage work: Drainage pipe 1,387m 16ea Pavement Work: Base 875a Surface 1,108a

    Road Bed Work for Ulsan Shigaji Railway Shifting Project

    Order
    KORAIL
    Period
    1988.11~1991.12
    Scale
    Expansion 5.866Km Earth Work: Cutting 116,066m3 Banking 147,826m3 Bridge Work : 2,204m 5 Bridges P.C BEAM Tunnel Work: Tunnel 781m 3 Tunnels
  • T-5 Dolphin Mooring Capacity Development Project

    Order
    SK Corp.
    Period
    1984.02~1984.05
    Scale
    Remove one existing BREASTING DOLPHIN , Riprap 2,534m3, CLAY 1,781m3, PILE driver 18 ea
    더보기

    ICHEON-MUNGYEONG RAILWAY SECTION NO.8

    ICHEON-MUNGYEONG RAILWAY SECTION  NO.8

    Order
    Smart Rail Corp.
    Scale
    - Extension L : 11.980km - Bridges : 0.490km (3ea) - Tunnel : 10.620km (2ea) - Station : 313ea (1point) - L: 14.728km
    더보기

    Gunjang National Industry Complex (Janghang Area) Revetment Road Construction

    Order
    Korea Land Corporation
    Scale
    ○ Revetment (L=6,032M) - Soft Ground Work: S.C.P 98,218m, S.C.P Sandmat 267,034㎥, P.B.D 37,487m - Riprap and Armor Stones: Riprap 1,270,553㎥, Armor Stones 168,659㎥, Sediments 223,118㎥ - T.T.P(3.2~12.5TON) : 59,397EA - Surface Concrete: 133,951㎥ ○ Revetment Road Construction (L=5,906M, B=32M) - Earth Work: Cutting 111,878㎥, VTM 130,930㎡, Dredging Back Filling 1,938,543㎥ ○ 2 Lock Gates
    더보기

Gumi Industrial Parks Arterial Road Construction Phase 1

The Business Performance details view. can you check Work Scope, Order, Period
· Location 393, Maehoi-ri, Imgo-myeon, Youngchun-si, Gyungbuk
· Order Korea Water Resource Corp.
· Period 1989.12~1993.07
· Scale Road Expansion L= 13.68Km B=18.5m Earth Work: Cutting 95,062m3 Banking 308,435m3 Drainage Work : Drainage pipe 2,346m 60ea, Conduit 69m 43ea Structure Work: Bridge 447.17m 4ea Pavement Work: Surface 2,505a Base 2,318a

Changwon-Jangyoo Road Construction Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Namsan-dong, Changwon-si~Mugye-ri, Jangyu-myeon, Gimhea-gun, Gyungnam
· Order Gyungnam
· Period 1989.11~1994.02
· Scale Road expansion L=6.96Km B=12.0m Earth Work: Cutting 646,082m3 Banking 403,879m3 Drainage work: Drainage pipe 1,387m 16ea Pavement Work: Base 875a Surface 1,108a

Road Bed Work for Ulsan Shigaji Railway Shifting Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Sangye-dong, Yeochun-dong, Nam-gu, Ulsan
· Order KORAIL
· Period 1988.11~1991.12
· Scale Expansion 5.866Km Earth Work: Cutting 116,066m3 Banking 147,826m3 Bridge Work : 2,204m 5 Bridges P.C BEAM Tunnel Work: Tunnel 781m 3 Tunnels

T-5 Dolphin Mooring Capacity Development Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Nam-gu, Ulsan
· Order SK Corp.
· Period 1984.02~1984.05
· Scale Remove one existing BREASTING DOLPHIN , Riprap 2,534m3, CLAY 1,781m3, PILE driver 18 ea

ICHEON-MUNGYEONG RAILWAY SECTION NO.8

  • ICHEON-MUNGYEONG RAILWAY SECTION  NO.8
The Business Performance details view. can you check Work Scope, Order, Period
· Location Icheon-si ~ Mungyeong-si, Korea
· Order Smart Rail Corp.
· Scale - Extension L : 11.980km - Bridges : 0.490km (3ea) - Tunnel : 10.620km (2ea) - Station : 313ea (1point) - L: 14.728km

Gunjang National Industry Complex (Janghang Area) Revetment Road Construction

The Business Performance details view. can you check Work Scope, Order, Period
· Location Janghang-eup/Maseo-myeon/ ,Seocheon-gun, Chungcheongnam-do
· Order Korea Land Corporation
· Scale ○ Revetment (L=6,032M) - Soft Ground Work: S.C.P 98,218m, S.C.P Sandmat 267,034㎥, P.B.D 37,487m - Riprap and Armor Stones: Riprap 1,270,553㎥, Armor Stones 168,659㎥, Sediments 223,118㎥ - T.T.P(3.2~12.5TON) : 59,397EA - Surface Concrete: 133,951㎥ ○ Revetment Road Construction (L=5,906M, B=32M) - Earth Work: Cutting 111,878㎥, VTM 130,930㎡, Dredging Back Filling 1,938,543㎥ ○ 2 Lock Gates