본문 바로가기 주 메뉴 바로가기

We Build the Great Great Life, Great World

BUSINESS Business Performance

  • SK HYNIX M14 PH-2 WWT Project

    Order
    SK Hynix
    Period
    2015.10~2017.04
    Scale
    100,000 Ton/D
    Perform Form
    EPC
    더보기

    SK HYNIX ?M14 Project PH-2 Project

    Order
    SK Hynix
    Period
    2015.10~2016.12
    Scale
    Clean Room 10,000 pyeong
    Perform Form
    EPC
    더보기

    Goseong High thermal power plant construction ( castles Green Power Project)

    Work Scope
    PC
    Order
    SPC
    Period
    2015.09~2021.04
    Scale
    2,080MW (1,040 MW x 2)
    Perform Form
    IPP Sponsor+ EPC
    더보기
  • Daeyeon SK VIEW Hills

    Period
    2015.09~2018.04
    Scale
    Apts. 1: 4 floors below ground, 26 floors above ground 11 buildings Apts. 2: 2 floors below ground, 19 floors above ground 1 buildings total 1,174 units Gross Area: 167,942.90㎡
    더보기

    SK HYNIX WWT CAPA-UP Project

    Order
    SK Hynix
    Period
    2015.08~2015.12
    Scale
    25,000 Ton/D → 50,000 Ton/D
    Perform Form
    EPC
    더보기

    SK HYNIX WAFER TEST Project

    Order
    SK Hynix
    Period
    2015.08~2016.09
    Scale
    Construction area - 2nd floor : Clean Room 3,667Py - 3-4 layers: Frame construction 17,131Py
    Perform Form
    E/C
    더보기
  • SKHynix Icheon Remodeling Construction in the main management assistance

    Period
    2015.08~2015.12
    Scale
    Gross Area : 8,528m2
    더보기

    Munjeong 1-2 BL Industry Center

    Period
    2015.08~2017.11
    Scale
    Land Area : 4,443 pyung , Gross Area : 45,346 pyung
    더보기

    CDP-3 Project

    Order
    SK Chemical
    Period
    2015.08~2017.03
    Scale
    CHDM 14,000 ton / Year Production
    Perform Form
    C
  • M14-M10A logistics BRIDGE Building construction

    Period
    2015.07~2015.12
    Scale
    Gross Area : 1,013m2
    더보기

    Buoy Ulsan Relocation Corporation ( including Donghae-1 gas pipeline relocation )

    Order
    Korea National Oil Corporation
    Period
    2015.07~2017.10
    Scale
    ○New pipelines and oil relocation Buoy -BUOY Relocation : SPM Refur - New pipeline (3.6km), remove the existing pipeline (0.6km) ○ Pipeline relocation - New gas pipeline (5.6km), remove the existing pipe (1.7km) ○ 1 construction type (operating bases) ○ Soil Improvement : DCM Corporation (364m X 32m)
    더보기

    Subway Jinjeop line(Danggogae ~ jinjeop ) double-track train the first tool construction

    Order
    Korea Rail Network Authority
    Period
    2015.06~2019.12
    Scale
    [ Total length L = 4.576Km] - Tunnel 3.801Km / 1 places - Station ( underground layer 3 ) 0.203Km / 1 places - Excavation Box 0.270Km - Main supply and exhaust ventilation small four places - Substations and other function rooms
    더보기

SK HYNIX M14 PH-2 WWT Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Icheon-si, Gyeonggi-do, Korea
· Order SK Hynix
· Period 2015.10~2017.04
· Scale 100,000 Ton/D
· Perform Form EPC

SK HYNIX ?M14 Project PH-2 Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Icheon-si, Gyeonggi-do, Korea
· Order SK Hynix
· Period 2015.10~2016.12
· Scale Clean Room 10,000 pyeong
· Perform Form EPC

Goseong High thermal power plant construction ( castles Green Power Project)

The Business Performance details view. can you check Work Scope, Order, Period
· Location Goseong-gun, Gyeongsangnam-do, Korea
· Work Scope PC
· Order SPC
· Period 2015.09~2021.04
· Scale 2,080MW (1,040 MW x 2)
· Perform Form IPP Sponsor+ EPC

Daeyeon SK VIEW Hills

The Business Performance details view. can you check Work Scope, Order, Period
· Location 1346-345 Area, Daeyeon-dong, Nam-gu, Busan, Korea
· Period 2015.09~2018.04
· Scale Apts. 1: 4 floors below ground, 26 floors above ground 11 buildings Apts. 2: 2 floors below ground, 19 floors above ground 1 buildings total 1,174 units Gross Area: 167,942.90㎡

SK HYNIX WWT CAPA-UP Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Icheon-si, Gyeonggi-do, Korea
· Order SK Hynix
· Period 2015.08~2015.12
· Scale 25,000 Ton/D → 50,000 Ton/D
· Perform Form EPC

SK HYNIX WAFER TEST Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Cheongju-si, Chungcheongbuk-do, Korea
· Order SK Hynix
· Period 2015.08~2016.09
· Scale Construction area - 2nd floor : Clean Room 3,667Py - 3-4 layers: Frame construction 17,131Py
· Perform Form E/C

SKHynix Icheon Remodeling Construction in the main management assistance

The Business Performance details view. can you check Work Scope, Order, Period
· Location 2091, Gyeongchung-daero, Bubal-eup, Icheon-si, Gyeonggi-do, Korea
· Period 2015.08~2015.12
· Scale Gross Area : 8,528m2

Munjeong 1-2 BL Industry Center

The Business Performance details view. can you check Work Scope, Order, Period
· Location 641-3, Munjeong-dong, Songpa-gu, Seoul, Korea
· Period 2015.08~2017.11
· Scale Land Area : 4,443 pyung , Gross Area : 45,346 pyung

CDP-3 Project

The Business Performance details view. can you check Work Scope, Order, Period
· Location Ulsan-si, Korea
· Order SK Chemical
· Period 2015.08~2017.03
· Scale CHDM 14,000 ton / Year Production
· Perform Form C

M14-M10A logistics BRIDGE Building construction

The Business Performance details view. can you check Work Scope, Order, Period
· Location 2091, Gyeongchung-daero, Bubal-eup, Icheon-si, Gyeonggi-do, Korea
· Period 2015.07~2015.12
· Scale Gross Area : 1,013m2

Buoy Ulsan Relocation Corporation ( including Donghae-1 gas pipeline relocation )

The Business Performance details view. can you check Work Scope, Order, Period
· Location Dang-wol-ri, Ulju-gun, Ulsan, Korea land and sea area.
· Order Korea National Oil Corporation
· Period 2015.07~2017.10
· Scale ○New pipelines and oil relocation Buoy -BUOY Relocation : SPM Refur - New pipeline (3.6km), remove the existing pipeline (0.6km) ○ Pipeline relocation - New gas pipeline (5.6km), remove the existing pipe (1.7km) ○ 1 construction type (operating bases) ○ Soil Improvement : DCM Corporation (364m X 32m)

Subway Jinjeop line(Danggogae ~ jinjeop ) double-track train the first tool construction

The Business Performance details view. can you check Work Scope, Order, Period
· Location Sanggye-dong, Nowon-gu, Seoul. ~ Jinjeop-eup, Namyangju-si, Gyeonggi-do, Korea
· Order Korea Rail Network Authority
· Period 2015.06~2019.12
· Scale [ Total length L = 4.576Km] - Tunnel 3.801Km / 1 places - Station ( underground layer 3 ) 0.203Km / 1 places - Excavation Box 0.270Km - Main supply and exhaust ventilation small four places - Substations and other function rooms